Subcontractor onboarding checklist for California GCs: the compliance packet

Updated · HatBench

Short answer
  • Before day one, collect: a signed subcontract, a W-9, the sub's CSLB license checked for the right classification, a certificate of insurance naming you, the additional insured endorsement if required, and workers' comp proof or CSLB's exemption on file.
  • During the job: lien waivers with each payment, renewed certificates before policies end, and a fresh CSLB check before each payment.
  • Keep every paper dated. The packet is what your auditor, owner or lender asks for.

This guide is for general contractors. It's a plain-language summary as of November 6, 2026, not legal advice. Your own contract forms and your insurer's requirements come first.

Before the sub starts

  • Signed subcontract. Scope, price, schedule, payment terms, retention and insurance requirements in writing.
  • W-9. For your 1099 reporting.
  • CSLB license, right classification. Look it up on CSLB's license lookup and match the classification to the work. See license classifications and scope.
  • Certificate of insurance naming you. General liability (and auto, if they drive on site), with you as certificate holder. See the certificate checklist.
  • Additional insured endorsement, if your contract requires it. See additional insured endorsements.
  • Workers' comp. A certificate, or CSLB's record showing an exemption because the sub has no employees (CSLB form 13L-50). See exemptions.

While the job runs

Keep it in one place

HatBench My Subs keeps a dated paperwork checklist for each sub (W-9, subcontract, certificate, endorsement, workers' comp), tracks the CSLB record and general liability dates, groups subs by project, and prints the whole packet status on one compliance report. Free during the private beta.

Checklist

  • Signed subcontractScope, price, schedule, pay terms, insurance.
  • W-9Before the first payment.
  • CSLB license checkedActive, right classification, dated.
  • Certificate naming youGeneral liability dates noted.
  • Endorsement copyIf additional insured is required.
  • Workers' comp or exemptionCertificate, or CSLB's record.
  • Lien waivers each paymentConditional, then unconditional.

Common questions

What should a GC collect from a sub before work starts?
A signed subcontract, a W-9, a CSLB license check for the right classification, a certificate of insurance naming you, the additional insured endorsement if your contract requires it, and workers' comp proof or CSLB's exemption on file.
Do I need a sub's workers' comp if they have no employees?
A sub with no employees can file an exemption with CSLB, which shows on their license record. Check it, keep a dated copy, and check again before each payment: if they hire, they need coverage.
How long should I keep the packet?
Keep it at least through your workers' comp audit for that policy year and as long as your contract, your insurer or your lender requires. Ask your own advisor for a firm number.

General information for California contractors, current as of November 6, 2026. It isn't legal advice; rules change, so check the official source linked above.